Changed the rules for connecting gas to a private house
On February 9, numerous amendments that were made to the rules for connecting residential buildings to the centralized gas supply system come into force.
Let us briefly consider what the main changes are and how they will affect citizens who own private houses.
1. The procedure for calculating tariffs for technological connection to a gas pipe is being specified.
They should be differentiated depending on the list of gas connection works, the diameter and material of the gas pipeline pipes and the technical characteristics of the general gas supply system.
Regional tariff services are required to approve tariff rates for gas connection, broken down by individual categories of consumers.
The fee for connecting to the gas pipeline for citizens should be set in the range of 20 to 50 thousand rubles, and this amount now includes VAT. This will reduce the total cost of connecting to gas for individuals.
However, all expenses for supplying gas networks to a citizen's land plot are now paid separately, in excess of the established 50,000 rubles.
2. The rules for connecting to gas distribution networks distinguish three categories of consumers, depending on which they will differ somewhat.
The first category - consuming up to 20 cubic meters of gas per hour, with a distance to the point of connection to the gas pipeline up to 200 m.
The second category - consuming no more than 500 cubic meters. m of gas, the distance to the connection point is no more than 500 m (in rural areas), 300 m (in urban areas) on the territory of one settlement.
And the third category differs from the second only in that for connection it is necessary to cover the territory of two or more settlements.
3. The procedure for connecting the house to gas will include the following steps:
- sending a request by a citizen to provide technical conditions for connecting to the network (including via the Internet with the ability to track the progress of the application). The request can now include a request for a preliminary calculation of the cost of technical connection to the gas network,
- issuance of specifications,
– fulfillment of technical conditions and execution of an act on the readiness of house networks for gas connection,
- the actual connection of the networks of the house to the gas distribution pipe with the preparation of the relevant act.
The rule is canceled that it is possible to connect housing to the gas network without prior issuance of technical specifications and immediately conclude a connection agreement if the gas consumption does not exceed 300 cubic meters. m per hour.
4. The period of validity of the technical conditions for connecting the house to the gas network issued to the applicant has been significantly reduced.
Now it will be 70 working days.
5. The terms for sending the applicant a draft agreement for connecting the house to the gas network are reduced:
- up to 5 working days from the date of receipt of the application - if the gas pipeline passes within the boundaries of the site where the house is located; - up to 30 working days - with consumers of categories 2 and 3, and up to 15 working days - in all other cases.
6. The maximum terms for connecting a house to gas have been specified:
- for category 1 consumers - from 9 months to 1 year, for category 2 - from 1.5 to 3 years, for category 3 - from 2 to 4 years, depending on individual conditions.
7. Reduced terms for paying for gas connection:
- 50% - within 11 working days from the date of conclusion of the contract, the remaining 50% - 11 working days from the date of signing the act of connection.
Haven't gasified your home yet? Getting ready for the new rules!
Form of permission to work in the protected zone of the main gas pipeline
Download sample document
FORM OF WORK PERMIT FOR PROTECTION ZONE
Stages of work performed in the presence of a representative of the operating organization:
Safety measures during the production of work (indicate the conditions under which the work will be carried out: specifically, precautionary measures, instructions that must be followed). Responsibility for compliance with safety measures and the safety of the existing pipeline and its structures in the process of work is carried out by the work manager
Responsibility for compliance with safety measures and the safety of the existing pipeline and its structures in the process of work is carried out by the work manager.
Written notification of the call of a representative for work performed in his presence is transmitted to the operating organization 5 days in advance.
before starting this work.
3. Production of works (their stages) after the period specified in the permit is prohibited.
Form to connect download to connect to from the owner sample form - How can I download the file?
Do I need the consent of all owners of the site for gasification
related articles
How to check out of an apartment to nowhere
How to reflect in the dismissal order deduction for used vacation
contract processing procedure
Nichego.Net 12.08.2003, 11:02 # flagrant violation of the legislation of the Russian Federation, article 274 of chapter 17 of the Civil Code of the Russian Federation (this is the chapter on land ownership) reads: “Laying operational lines, power lines and communications, pipelines, providing water supply and melioration without consent the owner of the land is prohibited”, in addition, restrictions are imposed on the laying territory, i.e. you cannot dig at a distance of 6 meters from the pipe and do not have the right to erect buildings and lay communications there. And even more so, her signature should be under the gasification project for neighbors. states: “The owner of a land plot has the right to use at his own discretion everything that is above and below the surface of this plot” ...
Do I need to take permission from the owners of the gas pipeline to connect gas
Home Questions and orders Gasification in case of disagreement of the owners Ask faster than read. Ask the lawyers a question! 8189 lawyers are waiting for you The author of the question is Russia I am the owner of a land plot for individual housing construction in a cottage settlement.
But one problem has arisen: some of the land owners do not want to get gasified for money (they are waiting for it to be done at the state expense) and do not want to give permission to lay a gas pipeline through shared ownership.
Is the consent of the owners of part of the household required for gasification?
Gas / Gasification and gas supply House for two owners.
Each of the owners wants to arrange a separate gas connection.
Do I need to get neighbor's consent? Such questions often come from visitors to EnergoVOPROS.ru We are publishing explanations from specialists of the State Unitary Enterprise MO Mosoblagaz on this matter.
A house for two owners, is it necessary to coordinate the gasification of one's half with a neighbor? Question: Tell me, please, I want to apply for the technological connection of the house, ½ of which belongs to me, and the other part belongs to my neighbor.
The house is divided into two non-communicating parts and has separate entrances. Each of us owns his own piece of land.
I want to set up a separate process connection from the central distribution without using a neighbor's connection.
Do I need permission from the second owner of the house for gasification?
- Categories
- The property
- Good day! I am the owner by inheritance of a part of a village residential building in which I am registered and live permanently.
I'm crying for the light. The village is gasified. When filling out an application for connecting a residential building, the gas workers asked for the consent of another owner of a part of the same house, which he also inherited.This owner of a part (share) of the village house is registered and lives in another region of the country.
The need for technical specifications for gas supply at home and where to get them
The feasibility of connecting to the gas network from a financial point of view can be determined at a preliminary stage, going beyond your site. Usually, on poles or fences, in the case of passage near the gas main, there are yellow plates indicating the main parameters of the line passing underground.
In any gasified settlement, on a specially fenced area, you can see a gas distribution substation, where gas is supplied under high pressure - after the pressure is reduced by reducers, it is distributed through the streets.
All these data indicate that the gasification of your site can be carried out quite simply and without significant costs.
All gas pipeline networks belong to some organization, in the cities Gorgaz is such a service, and it issues the relevant documents. For many cities and towns, only this organization is enough to get the technical specifications for gas supply.
In suburban or agricultural areas remote from cities, the relevant permit is issued by regional organizations or gas supply companies that own the gas pipeline.
In the Moscow region, technical conditions are provided and issued by Mosoblgaz, in areas near other large cities, technical conditions are issued by similar regional services (Nizhegorodoblgaz, Bryanskoblgaz). In more remote suburban regions, such services are usually Open Joint Stock Companies (OJSC) or Limited Liability Companies (LLC) that own the gas supply line (Sibirgazkomplekt LLC, Gazprom Transgaz LLC).
list of files
Guidelines for calculating the amount of payment for the technological connection of gas-using equipment to gas distribution networks and (or) standardized tariff rates that determine its amount, 2014
.zip, 254 Kb
Decree No. 50/1 dated 23.12.2016 “On establishing fees for the technological connection of gas-using equipment to gas distribution networks in the Stavropol Territory for 2017”
Decree of December 23, 2016 No. 50/2 “On the establishment of standardized tariff rates and formulas for calculating fees for technical connection of gas-using equipment to gas distribution networks on the territory of the UK for 2017"
The request form for the provision of those. conditions for connection (technological connection) for legal entities.
Application form for connection (technological connection) to the gas distribution network for legal entities.
Request form for the provision of technical conditions for connection (technological connection) for individuals (individual entrepreneurs).
Application form for connection (technological connection) to the gas distribution network for individuals (individual entrepreneurs).
Request for calculation of the planned maximum hourly gas consumption for the issuance of technical conditions.
Form for collecting initial data for calculating the maximum hourly gas consumption for the issuance of technical conditions.
The procedure for making an advance payment under the connection agreement, 2017
Decree No. 66/2 of the RTC of the Stavropol Territory "On the establishment of fees and standardized tariff rates for determining the amount of fees for technological connection to the gas distribution networks of the UK for 2018" dated 12/28/2017
Order No. 15 dated January 23, 2018 “On the establishment of a technical commission to determine those. the possibility of connection (technical connection) of capital construction facilities to gas distribution networks with the possible participation of the applicant"
Order of the Federal Antimonopoly Service of Russia dated August 16, 2018 N 1151/18 "On approval of the Guidelines for calculating the amount of payment for the technological connection of gas-using equipment to gas distribution networks and (or) the size of standardized tariff rates"
Decree of December 28, 2018 No. 61/1 "On the establishment of fees and standardized tariff rates for determining the amount of fees for the technological connection of gas-using equipment to gas distribution networks in the territory of the UK for 2019"
Standard form of an agreement on connection (technological connection) of capital construction facilities to the gas distribution network
Connection service provision regulation
Technical conditions for connecting water supply
The technical conditions indicate not only the main characteristics of the point at which the water supply is connected. The scope and conditions specified in the documentation depend on the area and area in which the technical work on the connection will be carried out. All prescribed provisions usually occupy 1-3 sheets.
A connection is an installation designed to supply gas by directing one or more users. The connection will be requested by a person or entity that needs a new gas supply point or an expansion of an existing one, regardless of whether the consumer will be a consumer or not.
Once the link is requested, the distribution company will have to notify the applicant.
- Connection fee.
- Construction period.
- Delivery start date.
- As well as budget equity.
The timeframe the distribution company has to communicate is 15 days if you need a specific project to connect and 6 days for the rest of the course.
When compiling the documentation, the characteristics that the connecting parts must have are taken into account. Each user can learn how to coordinate and submit project documentation. It is better to choose a design organization on the advice of a water supply service.
In the event that the applicant accepts an offer from a distributor, he is obliged to complete the delivery in accordance with the agreed terms and conditions, leaving her in a position to start the delivery. If the applicant rejects this proposal, he may be sent in writing to the competent authority of his Autonomous Community, which must resolve the issues raised within 20 days.
The marketer will inform you of the timeframe in which the change will be effective. The most common thing for internal clients is that this change occurs on the next meter reading cycle. Changing the supplier is a very simple process for the consumer, since the withdrawal procedures of the previous contract are carried out by the new marketer with whom the contract is signed.
What you need to present to individuals:
- Passport, copy of passport;
- Documents of the taxpayer;
- The right to own a land plot;
- Description of the situation on the site where the land ownership is indicated on the map;
- The amount of water to be used.
A situational plan and a plan describing the location of the site can be obtained from the Administration. Before looking for a design organization and signing a contract, it is necessary to obtain technical specifications. The procedure for obtaining technical specifications by legal entities is different - they must provide a greater number of documents.
Prices inevitably change depending on the situation related to the opening of your gas meter. From simple commissioning to connecting a meter already installed in the network in an emergency, it's time to make a turn. Advantages applied in cases, and therefore the following.
Prices associated with the operation and opening of a gas meter
With regard to emergency opening, 24 hours is indicated as an indication.If the request is made before 3 pm on the same day, a technician can be dispatched in the afternoon. In addition to the prices already quoted for opening a gas meter, connection work must also be taken into account.
Design of the gas supply system
Decree N 1314 allows gasification of objects without drawing up specifications, however, designing in third-party organizations that are not related to the GDO is difficult due to the lack of data on the point of connection of an individual line to a common gas pipeline. After receiving the TS, you can contact a licensed design organization on the recommendation of the GDO (sometimes indicated in the TS) or choose it yourself, in the latter case, you should expect minor nit-picking and problems with the project.
If the design of the system is carried out by GDO specialists, technical conditions are not required, but the quality of work in many cases causes complaints - the level of state specialists, as a rule, is lower than the individual developers of a private design company.
The process of connecting the cottage to the highway step by step
The process of connecting a house to a common gas main consists of the following steps:
- sending an executive GRO application for the provision of technical specifications for connecting a house;
- issuance of specifications for gas supply in a private house;
- sending the executive organization an application for drawing up an agreement on connecting the facility to the gas main in case of a positive decision of the previous issue;
- drawing up a connection agreement;
- performance of work on connecting the facility to the gas network in accordance with the technical conditions and the concluded contract;
- obtaining permission from the relevant services in a legislative manner to put the gas supply line into operation after the installation of the equipment;
- drawing up acts: on connecting the house, delimitation of property belonging to the parties and responsibility for its operation.
Where are the documents for obtaining gas
Specifications are drawn up at the location of the object. For registration of technical specifications for gas, documents are submitted according to the list provided by the local gas supply authority.
Please contact your local municipality before completing the documentation. The administration will provide information within 2 days on where to get technical conditions for gas.
How to get technical conditions for gas
After contacting the gas supply authority, documents are submitted according to the list of the gas supply service in your region.
Standard list of documents:
- Application for technical conditions. Served by the owner of the house or a person representing the interests of the owner.
- A copy of the passport of the owner of the gasified house.
- Identification code assigned by the gas supply authority. Issued in the form of a certificate.
- Documents certifying the applicant's ownership of the gasified facility.
For gasification, originals and copies of documents are provided.
Terms of obtaining specifications
After we handed over the documents to the gas supply service, "GORGAZ" or "RAIGAS". A response must be provided within 14 days. If the answer is yes, prepare the documents and connect the gas. A negative answer must be substantiated in writing and confirmed by an official or official. The legitimacy of the refusal is checked in the supervisory body "TECHNADZOR".
Specifications for gas are provided not only for finished facilities, but also for facilities in the planning stage. For objects at the planning stage, an additional list of documents is being prepared.
- Permission to conduct construction work. Issued by local authorities.
- Documents confirming the ownership of the land on which the gasification facility is being built.
- Copy of those passports of the gasification facility under construction. The points of the law on gasification are coordinated in the passport.
After the commissioning of the gasified facility, the following documents are added:
- Act on the commissioning of the gasification facility.
- Those. object passport or certificate of state registration of ownership of real estate.
- Situational plan of the gasification facility. It indicates the boundaries of the object.
- Estimate with thermal calculations.
Gasification documents are submitted personally or third parties are involved. To involve third parties, a notarized power of attorney is issued. A copy of the power of attorney is attached to the submitted documents. On the basis of the power of attorney, the authorized person has the right to represent your interests in the authorities for the collection of documents.
Each settlement has its own characteristics of gasification. Before collecting documents, please read the list of documents and requirements related to your region.
It is recommended to get preliminary advice from the territorial gas supply authority. The consultation will reduce the risk of re-collection and submission of documents.
The organization that issued the technical specifications is obliged to fulfill its obligations within 1 year. If incorrect calculations of the load on engineering networks are found, an application is submitted. If the application is not submitted on time, it is considered that the organization has fulfilled its obligations under the contract.
In the event of a change in the owner of a gasified facility, the new owner has the right to take advantage of the conditions issued by the previous owner of the facility.