Documentation
Documents submitted by the applicant
I. Documents to be submitted:
- Request for the issuance of technical conditions.
- Passport or other identity document.
- A document confirming the authority of the representative of the applicant.
- Copies of constituent documents:
- the charter of the organization (as amended) or the Memorandum of Association;
- minutes of meetings of the board of directors/meetings of participants (on the appointment of managers);
- an order appointing a director;
- certificate of registration of a legal entity;
- tax registration certificate.
- Title documents for a land plot (certificate of ownership, lease agreement, etc.) - for the owner of the land plot.
- Cadastral passport of the land plot on which it is planned to carry out the construction of a capital construction object or on which a reconstructed capital construction object is located.
- Urban planning plan for the permitted construction (reconstruction) of capital construction projects.
- Situational plan for the location of the object with reference to the territory of the settlement (if any).
II. Documents submitted at the initiative of the applicant:
The planned value of the required load (in the presence of relevant information, in any form).
Preparation of documentation required for connection to the water supply in a private house
When preparing to connect to the public water supply, the following steps must be taken to ensure compliance with the established administrative procedure:
make sure that there is a site plan with engineering and technical structures marked on it and laid communications;
Approximate view of the site plan with a detailed indication of all available elements
- submit an application to the water utility, the deadline for consideration of which is 1 month, and receive technical conditions there;
- with the documents received, apply to the sanitary and epidemiological station and write there an application for issuing an opinion regarding the connection to the central water supply;
- prepare a connection project by contacting a specialized organization licensed to perform such work;
- after registering the project in the water utility, it must also be registered with the SES;
- coordinate the implementation of earthworks with public utilities;
- conclude a contract for the performance of work with an organization that has the appropriate license and whose employees know how to connect to a water supply under pressure. Performing work on your own is considered an illegal tie-in and is fraught with rather large fines;
- upon completion of the tie-in work, invite the employees of the water utility to draw up an act on putting the system into operation;
- conclude a contract for the provision of water supply.
Video tie-in to the city system
A detailed report on the work of laying pipes and connecting the home system to a common highway.
The choice of the type of connection to the city sewer, or the decision to equip a private cleaning system, is best taken only after consultation with professionals. Specialists know what condition the central pipeline is in, how much it will cost to implement the project, what they can save on. You cannot work on your own. And for unauthorized tapping, you will have to pay a fine. To insure yourself from troubles, it is better to entrust the entire process to a construction organization - this will speed up the stage of paperwork and guarantee the uninterrupted operation of the sewer.
Connecting a private house to a central water supply (CV) is the most economical and convenient way to organize housing water supply. The only drawback of this option is the need to obtain a number of documents and permits, since unauthorized tapping into the central water supply is illegal.
In this article, we will consider the procedure for arranging the central water supply of a house, cottage or cottage. The necessary documents will also be considered and recommendations will be given on how to do all the work with your own hands.
Performing work on connecting to the main water supply
You can start work only after receiving all the necessary documents.
As we said above, the connection to the main water supply should be carried out only by an organization that has a special license.
Digging and arranging trenches can be done on your own
Work is usually performed in the following order:
a pipe is selected for supplying water to the house. Most often, preference is given to flexible, lightweight and non-corrosive HDPE pipes;
HDPE pipes for connection to the main water supply
- Procurement of required fittings. The purchase can be handled by both the organization that connects the private house to the water supply, and the owner of the house himself;
- a trench is torn off, and its bottom is carefully leveled and covered with a layer of rubble or gravel. When tearing off a trench, one should be guided by the norms that we have already talked about;
- the method of tapping into the main water supply is determined by the specialists of the organization performing this work;
- at the place where the pipe enters the house, a water well can be equipped. Sometimes the pipe can start right under the foundation;
Water well when entering a water pipe into the house
Connecting a pressure sewer system features
How to connect to the central sewer of a private house located on a plot in a recess? For the organization of water disposal in difficult areas, pressure systems are equipped.
Technical features of the arrangement and the advantages of pressure sewerage
When it is not possible to directly lay pipes to the central collector or pipe due to the rise of the terrain, it is necessary to equip a system with forced pumping of liquid between the tanks. This type of sewerage is called pressure.
Scheme of arrangement of local pressure sewerage
The withdrawal system consists of the following elements:
- The receiver is divided into a sump and a compartment for pumping. The first tank receives water from a domestic drain pipe. The output chamber is equipped with powerful pumping equipment. From the reservoir, the liquid is pumped through the pipeline to the next well.
- Lookout well. Water from the sump enters the revision well under pressure. Through the drain, the effluents flow into the common city pipe along the gravity line.
The arrangement of such a cleaning system is justified if it is possible to organize the simultaneous connection of several houses in order to reduce costs. Before deciding to connect, it is worth considering the possibility of installing an autonomous cleaning network.
1 What you need to know before connecting to CV
Among the advantages of connecting a private house to a central water supply, we highlight a serious reduction in the cost of organizing and operating water supply - the construction of a well or a well will not only cost more at the stage of their development, but will also be accompanied by the cost of repairing and cleaning such sources in the future.
Also, the city water utility provides a constant water quality - this statement is not fully true for all regions, however, if there are no problems with this in your area, then the only thing that will be needed to purify the water is an ordinary table filter.
Connecting to the water supply system is quite simple. You only need to collect the necessary technical acts and permits, after which a pipe is diverted from the central water supply to the house, which is laid below the level of soil freezing.
If the water pressure provided by the water utility suits you, you won’t even need to install a booster pump. An additional advantage will be the ability to connect to the central sewer, which is necessary for the discharge of domestic wastewater. If this is not possible, the work on arranging the sewerage will need to be done by hand.
However, there are often situations when connecting to a centralized water supply is problematic. The key factor is the outdated water utility, which is designed for a small number of users and is not able to provide sufficient water pressure. In cases where a thin stream of water flows from the tap, you can forget about the normal operation of the column, boilers, washing machines and other equipment.
You can increase the pressure by installing a special pump, which is mounted on a pipe and automatically turns on when water consumption points are operating. Keep in mind that when arranging an autonomous water supply for a private house from a well or a well, a pump will be required in any case.
Another problem of the central water supply can be low-quality water, which is not properly treated in public utilities. The other side of the coin is water, excessively chlorinated water. Here you will need a good filter, or an integrated water treatment system.
1.1
Required documents and connection procedure
To bring the central water supply to the house or cottage, you will need to collect the following documents:
- act of work on laying the pipeline;
- act for hydraulic testing of the system;
- the act of washing and sanitary cleaning of the water supply;
- help for installing the meter.
Direct work on bringing water into the house is carried out by specialists from the water utility or a licensed organization, but if, for any reason, you do everything yourself, you will additionally need to obtain acts for hidden work on extracting, backfilling the trench and adding sand.
Consider the sequence of actions when connecting:
The red tape with the documents ends here, it remains to contact the water utility and get a list of licensed organizations that can be engaged in laying and connecting the water supply. Installation of metering devices and their commissioning is carried out directly by the specialists of the water utility.
1.2
Features of connecting a house to CV (video)
Organizations involved in the provision of the service
Organizations accepting documents
- Sector 2 of the multifunctional center for the provision of state and municipal services of the Kurortny District
- Sector 1 of the multifunctional center for the provision of state and municipal services of the Petrodvorets district
- Sector 1 of the multifunctional center for the provision of state and municipal services in the Pushkinsky district
- Sector 2 of the multifunctional center for the provision of state and municipal services in the Pushkinsky district
- Sector 1 of the multifunctional center for the provision of state and municipal services in the Central District
Different conditions are provided for different objects, in connection with this, different types of specifications are distinguished
- technical conditions for the supply of electricity for the private sector;
- technical conditions for providing electricity to various facilities - shops, factories, warehouses;
- technical specifications for the purpose of reorganizing engineering networks, carrying out various types of repair work related to electrical networks.
Obligatory receipt of technical specifications is in certain cases:
- for facilities where electrical lines are located that have not been previously operated;
- when connecting a new user;
- for facilities where working power grids are located, but there is a need to increase the amount of power consumed;
- for facilities with operating power grids, for which there is a revision and change of external power supply schemes;
- to recover lost documents for already existing users.
Stages of obtaining technical conditions for connecting electricity
To obtain technical conditions for connection to electrical networks as quickly as possible, you must provide some information:
- purpose of the object or premises;
- official location of the object (indicating the legal address);
- the period of putting the facility into operation;
- indicate the required estimated power that the object will use.
Specification for connection to electrical networks is an important and mandatory document, which is drawn up before the start of electrical work.
What is required to apply for an electricity connection permit?
To obtain technical conditions for connecting to power grids, you will need to determine the following parameters:
- the amount of power used;
- origin of electrical energy;
- calculated current data;
- attachment points;
- agree on all requirements with the supplier of electrical energy, before the start of the execution of the document.
It is mandatory to carry out verification calculations of the operability of cables and additional devices:
- counters;
- transformers;
- switches;
- fuses.
It is also necessary to choose a place to place the counters and select their desired type. The technical conditions for connection to the power grid determine the necessary parameters of the devices used and the settlement means of electricity metering. The document prescribes according to environmental standards that are used during the start-up and operation of the electrical equipment used.
How to get technical specifications for connection to the power grid
Quite often, obtaining technical conditions for connecting electricity can be difficult, with self-registration, difficulties may arise, which will lead to additional time and effort. For a qualitative solution of the issue, it is better to contact competent specialists in this field. By contacting our company, you can be sure of a high-quality and efficient solution of the issue.
Competent specialists of our company will provide a range of services for obtaining technical conditions for electricity, efficiently and as quickly as possible help to correctly draw up the necessary documents in order to eliminate the possibility of errors in the future. Unfortunately, incorrect paperwork and insufficient information can lead to a number of troubles, the correction of which will be an undesirable waste for the client. Therefore, our company will help to reduce possible costs at the initial stage.
The entire process of development, execution and obtaining permission to connect to electrical networks is included in the list of mandatory services that you can get from us. Employees will provide a sample of specifications for connection to the power grid and carry out all the necessary procedures. Qualified specialists will make all the necessary calculations at a professional level, which will prevent problems with electricity in the future. On the Mosenergo City website you can find all the terms of cooperation, if you have any questions, the company's managers will provide comprehensive information on all points to obtain technical conditions for electricity. Only turning to professionals will allow you to get the desired result quickly and as efficiently as possible.
Document overview
For connection (technological connection) of objects, including apartment buildings, to a centralized cold water supply system, a standard contract is used.
One of the conditions of such a model contract was disputed.
By virtue of it, the organization of the water supply and sewerage sector carries out certain activities, including the connection of the facility to the networks.
In this case, the activities are carried out to the border of the applicant's site, and in the case of connection (technological connection) of an apartment building - to the border of the engineering and technical networks of cold water supply located in this house.
According to the applicant, such a condition unlawfully imposes additional obligations on the construction of water supply networks not only to the border of the relevant plot, but also from the border of the land to the apartment building. This increases the cost of building networks that are not included in the investment program.
The Supreme Court of the Russian Federation did not agree with this position and emphasized the following.
The Law on Water Supply defines the general rules for connection (technological connection) of capital construction facilities to centralized cold water supply and sanitation systems.
Thus, the point of such a connection, if technically possible, is installed on the border of the site on which the applicant's capital construction facility is located.
Meanwhile, the provisions of this act apply to relations related to the provision of public services for water supply, including cold, to the extent not regulated by other laws.
At the same time, by virtue of the Housing Code of the Russian Federation, the organization supplying the resources necessary for the provision of public services is responsible for such supplies to the boundaries of the common property in an apartment building and the boundaries of the external networks of engineering and technical support for this building.
Such a rule shall apply, unless otherwise established by an agreement with this organization.
At the same time, the Rules for the maintenance of common property in an apartment building provide that the internal engineering systems of cold and hot water supply are included in the common property.
Based on the analysis of the norms of these Rules, water supply networks located outside the outer boundary of the wall of an apartment building are not included in the common property of the owners of premises in an apartment building.
With this in mind, the disputed provision of the standard contract does not contradict the law.
To view the current text of the document and obtain complete information about the entry into force, changes and the procedure for applying the document, use the search in the Internet version of the GARANT system:
2 Works on laying and connecting the water supply
If you have the appropriate permission, then all installation work can be done by hand. The central water supply is a pipe with a diameter of 100-500 mm, which can be connected in two ways:
- welding method;
- use of clamp.
When using the welding method, the nearest shut-off valves are closed in the section of the central pipeline, after which a hole of the diameter specified in the project is cut out on the pipe, to which the thread (coupling) is welded. A full-bore crane is mounted on the coupling and a supply pipe is drawn from it to the house.
On obsolete central networks, shut-off valves may be missing or in a faulty condition, which leads to the need for tapping under pressure. It is possible to independently drill a pipeline through which water circulates only at a pressure of the working medium up to 4-5 atm.
Insertion with the use of overhead clamps is carried out when connected to pipelines made of polymeric materials - polypropylene and polyethylene pipes. To do this, the water is blocked and on the pipe, in the place where the hole will be drilled, a rubber or silicone expander is placed.Next, a clamp is applied and fixed (tightened with bolts), to which the thread is welded, a crane is mounted and a pipe is connected. In addition to the screed, it is desirable to fix the clamp with special epoxy adhesives that prevent its displacement during the thermal expansion of the pipe.
2.1
Installation of water supply inside the house
After the house has been supplied with water, it is necessary to draw up a scheme for distributing water pipes inside the building. When choosing a scheme, the following factors should be considered:
- number of points of water consumption;
- the presence of filters that lower the circulation pressure;
- the number of points of water consumption and the distance between them;
- the total length of the internal water supply.
In practice, two schemes are most often used - sequential (tee) and collector. The collector scheme shown in the image is suitable for small houses. It lies in the fact that one pipe is diverted from the water intake point, to which all water consumption points are connected. Its disadvantages are a decrease in the circulation pressure at the end of the circuit, however, this problem can be solved by installing a circulation pump.
The collector scheme is suitable for houses of any size, as it involves the installation of a collector at the water intake point, from which individual pipes are bred to each water consumption point. A shut-off valve must be installed for each section of the collector so that, if necessary, it is possible to shut off the water supply to the emergency section.
For distributing water supply inside the house, it is best to use polymer or metal-plastic pipes - this is a relatively cheap and durable option that surpasses steel counterparts in all performance characteristics. Connecting a shower cabin to the water supply, as well as columns and boilers, is rationally performed using elastic plastic corrugated pipes.
If the pipes of cold and hot water supply run in parallel, then the cold one should always be lower, so condensation will not form on it. The most common mistakes in the installation of internal water supply are:
- passing all pipes through one hole in the wall, with non-compliance with the minimum allowable distance between them;
- neglect of the installation of valves in front of plumbing fixtures;
- lack of thermal insulation of hot water pipes when they are placed in walls or an unheated underground.
And do not forget that according to the unspoken rule, hot water should be connected to the mixers on the right, and cold water on the left!
Storm system methods of arranging drainage
A difficult question is how to connect the storm drain of a private residential building to the city sewer. After all, the insertion of storm drains into a separate sewer is prohibited. It is necessary to develop separate conditions and conduct a pipeline to a common storm system. The most profitable option is a tie-in into a mixed sewer. The work can be combined and immediately bring a household and drainage pipe to the network.
Connection to the city storm main
There are 3 ways to ensure the drainage of rainwater from the site:
- A tie-in to the city highway.
- Diversion of the drainage system into the ground. Such a decision can lead to constant erosion of the soil, flooding of one's own and neighboring basements.
- Creating your own drainage system with a cleaning tank. Water is discharged into a container with filters, purified water is removed for reuse.
Insertion into the central sewer network
To connect to the city storm system, at the preparatory stage, documentation is drawn up, in the same way as for domestic drainage. The pipe is laid at an angle from the house to the entrance to the network. Use plastic pipes of smaller diameter.
The disadvantage of connection is the duration and organizational complexity of the procedure, dependence on the condition and cleanliness of the city pipe.
Autonomous system for a private house
The best solution for a private house is the arrangement of a drainage system. Water from the ground surface is fed into the drains, through pipes it is fed into the receiving tank. The well equipped with filters is connected in series with the next container for collecting purified water.
Autonomous storm water: water is reused
Such a storm sewer has the following advantages:
- Rainwater collection is organized over the entire area of \u200b\u200bthe site - in the yard, soil will not erode and water will not stagnate in the recesses.
- The efficiency of the system depends only on the correct installation and the correct calculation of the volume of receiving tanks.
- Autonomy: no need to pay for rainwater disposal, collect documents.