Example of budgeting 2 internal sewerage
(Examples are considered on the basis of TER-territorial unit prices, analogously and FER-federal unit prices)
Let's analyze an example of budgeting for internal sewage according to the project (specifications):
For example, download:
We open the VK Project 1-1.C on pages: 15 Sheet 4, 32 Sheet 4, 49 Sheet 4 and begin to draw up an estimate for the Internal Sewerage.
In the estimate, the sections are not in order as in the project, so do not be alarmed, there is nothing wrong with that,
The main thing is not to miss or forget anything.
Just like in the project, we divide everything into sections and in the estimate:
Section 1. K1 system (below 0.00)
Section 2. K1 system (above 0.00)
Section 3. System K2 (below 0.00)
Section 4. System K2 (above 0.00)
Section 5. Sanitary equipment
Consider which items according to the specifications correspond to which items according to the estimate:
Section 1. K1 system (below 0.00):
Item 1 of page 15, 32, 49 in the specifications corresponds to item 1 of estimate No. 2-5 for Internal Sewerage;
Paragraph 2 of pages 15, 32, 49 in the specifications corresponds to paragraph 2 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3 of pages 15, 32, 49 in the specifications corresponds to paragraph 3 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3 pp. 16, 33, 50 in the specifications correspond to paragraphs 4, 5 of estimates No. 2-5 for the Internal Sewerage;
Paragraph 6 of page 32 in the specifications corresponds to paragraph 6 of estimates No. 2-5 for Internal Sewerage;
Section 2. System K1 (above 0.00):
Paragraph 1 of page 15, 32, 49 in the specifications corresponds to paragraph 7 of estimates No. 2-5 for Internal Sewerage;
Paragraph 2 of pages 15, 32, 49 in the specifications corresponds to paragraph 8 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3 of pages 15, 32, 49 in the specifications corresponds to paragraph 9 of estimates No. 2-5 for Internal Sewerage;
Paragraph 4, pages 15, 32, 49 in the specifications correspond to paragraphs 10, 11 of estimates No. 2-5 for Internal Sewerage;
Section 3. K2 system (below 0.00):
Paragraph 1 pp. 16, 33, 50 in the specifications correspond to paragraphs 12, 13 of estimates No. 2-5 for Internal Sewerage;
Paragraph 2, pages 16, 33, 50 in the specifications correspond to paragraphs 14, 15 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3 of pages 16, 33, 50 in the specifications corresponds to paragraph 16 of estimates No. 2-5 for Internal Sewerage;
Paragraph 4, pages 16, 33, 50 in the specifications corresponds to paragraph 17 of estimates No. 2-5 for Internal Sewerage;
Paragraph 5 of pages 16, 33, 50 in the specifications corresponds to paragraph 18 of estimates No. 2-5 for Internal Sewerage;
Paragraph 6 of pages 16, 33, 50 in the specifications corresponds to paragraph 19 of estimates No. 2-5 for Internal Sewerage;
Section 4. System K2 (above 0.00):
Paragraph 1, pages 16, 33, 50 in the specifications correspond to paragraphs 20, 21 of estimates No. 2-5 for Internal Sewerage;
Paragraph 2 of pages 16, 33, 50 in the specifications corresponds to paragraph 22 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3 of pages 16, 33, 50 in the specifications corresponds to paragraph 23 of estimates No. 2-5 for Internal Sewerage;
Paragraph 4 of pages 16, 33, 50 in the specifications corresponds to paragraph 24 of estimates No. 2-5 for Internal Sewerage;
Paragraph 5 of pages 16, 33, 50 in the specifications corresponds to paragraph 25 of estimates No. 2-5 for Internal Sewerage;
Section 5. Sanitary equipment:
Paragraph 1 pp. 16, 33, 50 in the specifications correspond to paragraphs 26, 27 of estimates No. 2-5 for Internal Sewerage;
Paragraph 2, pp. 16, 33, 50 in the specifications correspond to paragraphs 28, 29 of estimates No. 2-5 for Internal Sewerage;
Paragraph 3, pages 17, 34, 51 in the specifications correspond to paragraphs 30, 31, 32 of estimates No. 2-5 for Internal Sewerage;
Paragraph 4, pages 17, 34, 51 in the specifications correspond to paragraphs 33, 34, 35 of estimates No. 2-5 for Internal Sewerage;
Paragraph 5, pages 17, 34, 51 in the specifications correspond to paragraphs 36, 37 of estimates No. 2-5 for the Internal Sewerage.
Copyrights to materials belong to the site
"To the estimator for the estimate" www.smetdlysmet.ru Any copying of the material is prohibited
How to make an estimate for an automatic irrigation system
Quite often, when landscaping the territories of parks, squares, as well as for uniform irrigation of lawns and fields, the installation of automatic irrigation systems is required. So how do you estimate the cost of installing these advanced irrigation solutions? Obviously, it is necessary to draw up a detailed and most correct estimate in order to estimate the costs of organizing automatic irrigation systems.In the work on drawing up estimates for the implementation of irrigation solutions as part of the improvement of parks and other infrastructure facilities, a novice estimator may encounter a number of difficulties. So, for the installation of nozzles, sprinklers and other elements of the automatic irrigation system, there are no direct prices in the database of territorial and federal regulations. Another thing is if you need to estimate the installation of a watering tap, digging trenches or laying pipelines - in our example, we offer various pricing options for these types of work.
An example of an estimate for an automatic irrigation system (sample without results)
Rationale | Name | Qty. | Main salary | EkMash | W/n Fur | Total |
TER24-01-033-01 | Installation of valves and socket valves with diameter: up to 20 mm approx. installation of nozzles, sprinklers and other auxiliary elements of the irrigation system | 1 PC. | 6,8 | 7,5 | ||
TERm07-04-028-04 | Submersible priming pump, weight 0.11 t approx. installation of a pump with a capacity of 20 cubic meters / hour | 1 PC. | 192,17 | 117,01 | 3,43 | 554,68 |
TERm11-03-001-01 | Devices mounted on metal structures, panels and consoles, weight: up to 5 kg approx. rain sensor installation | 1 PC. | 4,6 | 5,6 | ||
TERm10-02-041-03 | Electrical check and adjustment: information input-output channel (for the device of the automatic irrigation system control system) | 1 channel | 178,87 | 0,00 | 0.00 | 182,45 |
TERm12-14-022-02 | Motorized steel valve, nominal diameter: 50 mm approx. installing a half inch solenoid valve | 100 pieces. | 5806,84 | 1492,55 | 71,04 | 8071,43 |
TERm10-02-016-06 | Separately installed: converter or power supply (voltage stabilizer) | 1 PC. | 99,99 | 41,24 | 3,88 | 178,27 |
TERm08-02-141-01 | Cable up to 35 kV in finished trenches without coating, weight 1 m: up to 1 kg | 100 m cable | 94,15 | 79,67 | 3,67 | 241,76 |
FSTS-21.1.06.09-0048 | Power cable with copper conductors in a PVC sheath without a protective cover: VVG, voltage 0.66 kV, number of cores - 2 and cross section 2.5 mm2 | 1000 m | 0,00 | 3306,38 | ||
TER16-04-002-01 | Laying of water supply pipelines from pressure polyethylene pipes of low pressure of medium type with an outer diameter: 20 approx. laying of HDPE pipes | 100 m pipeline | 1683,62 | 1380,11 | 158,89 | 3152,06 |
TER22-01-021-01 | Laying of pipelines from polyethylene pipes with a diameter: 50 mm | 1 km pipeline | 1663,64 | 2313,7 | 250,7 | 3990,33 |
TER24-01-033-03 | Installation of valves and non-return valves with a diameter of up to 50 mm approx. installation of ball and American valves | 1 PC. | 11,18 | 0,00 | 0,00 | 12,85 |
TER22-05-003-01 | Pulling steel pipes with a diameter of 100 mm into the case approx. polyethylene | 100 m of pipe laid in a case | 725 | 33,01 | 0,00 | 1689,29 |